Other
Demounting of 2 fire tanks in Nizhny Novgorod
ending 08/01/2016
The professional employees of the construction company "Triumph" have started demounting of 2 reinforced-concrete fire tanks at address: Nizhny Novgorod, Torfyanaya-Str., 30. on the 1st of June 2016
The following kinds of work have been carried out:
-
ground excavation (storage tanks have been filled up)
-
demolition works with the use of hydraulic breaker
-
garbage removal to yard with further recycling of wastes
Photos of the work