Other
Monolithic pool deck of a swimming pool pouring in the township Bolshoye Kozino in Nizhny Novgorod region
ending 07/02/2014
Pouring of a monolithic pool deck of a swimming pool and site improvements for an individual customer has been completed in the township Bolshoye Kozino in Nizhny Novgorod region.
Following kinds of works have been carried out on site:
-
site engineering; setting-out work, technical writing, work maintenance has been performed
-
earthworks – excavation, ground coat removal has been carried out
-
steel lashing, form handling
-
pool deck pouring
-
moisture-proofing and heat proof of pool deck
-
water handling system and water filtration system installation
-
tile paving and podium for swimming pool installation
-
bath-house finishing, building of terrace, roofing (metal tile roofing)
-
bordering of facades by weatherboard
-
perimeter walks and sidewalks installation; installation of borders, pavestone laying
Photos of the work