Reinforced-concrete raft foundation construction for LLC Vtorchermet NLMK Group Volga in Nizhny Novgorod
ending 12/06/2017
The professional employees of the construction company “Triumph” have started construction of the reinforced-concrete raft foundation construction on the 1st of December at address: Nizhny Novgorod, Kominterna-Str., 37; catch platform for safe check of railway cars has been constructed; total work content is 14,5 cum.
The following kinds of work have been carried out:
-
ground excavation
-
excavation pit planning
-
reinforce framework forming
-
construction and unlocking of formwork
-
pouring of foundation forepart
-
major part of foundation pouring
Work is now complete.