The professional employees of the construction company "Triumph" have completed work in warehouse roof repair with an area of 1500 sq.m. in Nizhny Novgorod. Work performance has become necessary, because the upstand of the roofing stainless steel sheet was out of place, and it has caused leaf distortion and oozing.
Time-worn roofing must be changed because of roof profile sheeting deformation and oozing.
Our company has carried out the following kinds of works:
-
Dismantling of time-worn coatings
-
stainless steel sheet laying (Joint the adjacent sheets by lapping them by one corrugation at the side)
-
roof insulation
-
intermediate layer installation
-
joint hermetization and overcloak of roofing material sheet